Parklinks South Tower completes massive concrete pouring 21 days ahead of schedule

Congratulations to the Parklinks South Tower ACE Team for completing the massive mat foundation concrete pouring 21 days ahead of target. The activity, originally targeted to finish on November 14, was completed last October 24, 2023. A total volume of 6,172 m3 of concrete, equal to 686 truck loads, was poured in a span of just 62 hours. The activity was conducted safely without any incident.

Kudos to the Parklinks South Tower ACE Team headed by Efren Mananquil, Ariel Camannong, Etong Paz, Jess Dela Peña, and Mark Balayan.

Parklinks South Tower is a 55-story residential building with a total land area of 4,002 sqm. and 313 units. Together with Parklinks North Tower, the development forms part of the 35-hectare mixed-use Parklinks estate bridging Quezon City and Pasig.

Congratulations!