Project : E-Services Building 2 (Convergy’s)
Owner : Ayala Land, Inc.
Location : Makati City
Scope of Work : Design and construction of eight  (8) level office covering gross floor plate 2,630.74 sq. m. with a total of 18,435.11 sq. m. Works includes civil, structural, electrical, mechanical, sanitary and plumbing works.
Completion Date : October  2005
    back to top »
 
Project : Market Market!
Owner : Liberty Real Holdings, Incorporated
Location : Fort Bonifacio Global City, Taguig, MM
Scope of Work : Construction of a 5-storey commercial complex with an approximate floor area of 150,000m² and a basement parking of 8000². Works include civil, structural, electrical, mechanical, sanitary and plumbing works
Completion Date : February, 2005
    back to top »
 
Project : E – Office Building (People Support)
Owner : Ayala Land, Inc.
Location : Makati City
Scope of Work : Design and Construction of five (5) level  office covering gross floor plate area 5,006 sq. m.  with a total of 25,030 sq. m. Works include civil, structural, electrical, mechanical, sanitary and plumbing works.
Completion Date : March 2005
    back to top »
 
Project : Greenbelt Redevelopment
Owner : Ayala Land, Inc.
Location : Ayala Center, Makati City
Scope of Work : Construction of a residential (approx. 7,970m²) and a commercial building (approx. 91,474m²).  Works include civil, structural, electrical, mechanical, sanitary and plumbing works.
Completion Date : December 2003
    back to top »
 
Project : Montgomery Place Clubhouse
Owner : Ayala Land, Inc.
Location : E. Rodriguez Sr. Avenue, Quezon City
Scope of Work : Construction of a two-level clubhouse with an approximate floor area of 736m².  Scope of  works includes civil, structural, architectural, electrical, mechanical, sanitary and plumbing works.
Completion Date : April 2003
    back to top »
 
Project : Ayala Greenfield Estates Clubhouse
Owner : Ayala Greenfield Development Corporation
Location : Brgy. Maunong, Calamba City
Scope of Work : Construction of a two-level clubhouse with an approximate floor area of 1,909m².  Scope of  works includes civil, structural, architectural, electrical, mechanical, sanitary and plumbing works.
Completion Date : April 2002
    back to top »
 
Project : Globe Telecom Corporate Offices
Owner : Globe Telecom
Location : Mandaluyong City
Scope of Work : General interior construction and fit out works on 3rd and 4th floors with an approximate area of 6,000m². Works include excavation, civil, structural, electrical, mechanical, sanitary and plumbing works.
Completion Date : March 2002
    back to top »
 
Project : Makro Store Batangas
Owner : Makro Pilipinas, Inc.
Location : Batangas City
Scope of Work : Design and construction of a single storey structure with a floor area of 7,488m² and a total lot area of 23,000m² The construction is comprised of selling area, entrance lot, food preparation area, canteen, cold storage room, delivery bay, parking lot, transformer/genset  rooms.             
Completion Date : February 2002
    back to top »
 
Project : Globe Telecom Cebu Building
Owner : Globe Telecom, Inc.
Location : Cebu Civic and Trade Center
Lahug, Cebu City
Scope of Work : Construction of Globe Telecom Cebu Building comprising of two (2) basements and six (6) upper floors.  The work includes civil works, architectural works, electro-mechanical works and electrical works.
Completion Date : October 15, 2001
    back to top »
 
Project : Union Church of Manila
Owner : Union church of Manila
Location : Makati City
Scope of Work : Construction of a 7 storey church (3 level basement and 4 level above ground with an approXimate area of 8,400m². Works include excavation, civil, structural, electrical, mechanical, sanitary and plumbing works, fire detection and alarm system
Completion Date : December 2001
    back to top »
 
Project : Makro Store Pampanga
Owner : Makro Pilipinas, Inc.
Location : Mabalacat, Pampanga
Scope of Work : Design and construction of a single storey structure with a floor area of 7,500m² and a total lot area of 22,000m² The construction is comprised of selling area, entrance lot, food preparation area, canteen, cold storage room, delivery bay, parking lot, transformer/genset  rooms.             
Contract Amount : PhP 55.80M
Completion Date : October 2001
    back to top »
 
Project : Ayala Entertainment Center
Owner : Cebu Holdings, Inc.
Location : Ayala Center Cebu
Scope of Work : Design and construction for the renovation of a two level entertainment center with an approx. floor area of 4,250 m². Scope includes civil, structural, architectural, electrical, mechanical, sanitary & plumbing works.
Completion Date : July 2001
    back to top »
 
Project : City Sports Club Cebu
Owner : Cebu Holdings, Inc.
Location : Cebu Business Park, Cebu City
Scope of Work : Construction of 6 level concrete structure (3 level below ground and 3 levels above ground with an approx. floor area of 29,500m² including bulk excavation. Scope includes civil, structural, architectural, electrical, mechanical, sanitary & plumbing works.
Completion Date : August 2001
    back to top »
 
Project : MRT-3 Ayala Station Project
Owner : Ayala Land, Inc.
Location : Makati City
Scope of Work : Construction of commercial space for retail connecting MRT-3 to Ayala Center
Completion Date : January 2001
    back to top »
 
Project : St. Scholastica’s College
Owner : Benedictine Sisters
Location : Ayala Westgrove Heights, Silang, Cavite
Scope of Work : Construction of a 3-storey school building with a floor area of 3,100 m².  Works include civil, structural, electrical, mechanical, sanitary and plumbing works.
Completion Date : March 2000
    back to top »
 
Project : Isuzu Cavite
Owner : Isuzu Automotive Dealership, Inc.
Location : Imus, Cavite
Scope of Work : Renovation of existing car service center and showroom.  Works include civil, structural, architectural, electrical, mechanical, sanitary and plumbing works.
Completion Date : November 1999
    back to top »
 
Project : Ayala Westgrove Heights Clubhouse
Owner : Ayala Land, Inc.
Location : Ayala Westgrove Heights, Silang, Cavite
Scope of Work : Construction of a two-level clubhouse with an approximate floor area of 2,112m².  Scope of  works includes civil, structural, architectural, electrical, mechanical, sanitary and plumbing works.
Completion Date : November 1999
    back to top »
 
Project : Amkor Anam Assembly & Test Building
Owner : Amkor Anam Pilipinas
Location : Laguna Technopark
Scope of Work : Construction of a two-storey building with a total floor area of 14,225m².  Scope includes site development, civil, structural, architectural, electrical, mechanical, sanitary and plumbing works, fire protection and alarm system
Completion Date : March 1998
    back to top »
 
Project : Integrated Microelectronics Bldg. A
Owner : Integrated Microelectronics Inc.
Location : Laguna Technopark
Scope of Work : Construction of a two-storey building with a total floor area of 11,252m².  Scope includes site development, civil, structural, architectural, electrical, mechanical, sanitary and plumbing works, fire protection and alarm system
Completion Date : March 1998
    back to top »
 
Project : Isuzu Mandaue
Owner : Isuzu Automotive Dealership, Inc.
Location : Basak, Mandaue City Cebu
Scope of Work : Design and Construction of a two-storey building with a showroom.  Works include site development, civil, structural, architectural, electrical, mechanical, sanitary and plumbing works.
Completion Date : June 1998
    back to top »
 
Project : Isuzu Alabang
Owner : Isuzu Automotive Dealership, Inc.
Location : Madrigal Business Park, Muntinlupa City
Scope of Work : Construction of a 4-storey building with a 3-storey workshop area and a showroom at the ground floor and a mezzanine.  Works include civil, structural, electrical, mechanical, sanitary and plumbing works.
Completion Date : November 1996
    back to top »
 
Project : Integrated Microelectronics Bldg. C
Owner : Integrated Microelectronics Inc.
Location : Laguna Technopark
Scope of Work : Construction of a single-storey building with a total floor area of 7,560m².  Scope includes site development, civil, structural, architectural, electrical, mechanical, sanitary and plumbing works, fire protection and alarm system
Completion Date : December 1996
    back to top »
 
Project : Integrated Microelectronics Bldg. D
Owner : Integrated Microelectronics Inc.
Location : Laguna Technopark
Scope of Work : Construction of a two-storey building with a total floor area of 19,760m².  Scope includes site development, civil, structural, architectural, electrical, mechanical, sanitary and plumbing works, fire protection and alarm system
Completion Date : May 1996
    back to top »
 
Project : Integrated Microelectronics Bldg. E
Owner : Integrated Microelectronics Inc.
Location : Laguna Technopark
Scope of Work : Construction of a two-storey building with a total floor area of 19,760m².  Scope includes site development, civil, structural, architectural, electrical, mechanical, sanitary and plumbing works, fire protection and alarm system
Completion Date : February 1996
    back to top »
 
Project : Integrated Microelectronics Bldg. F
Owner : Integrated Microelectronics Inc.
Location : Laguna Technopark
Scope of Work : Construction of a two-storey building with a total floor area of 4,736m².  Scope includes site development, civil, structural, architectural, electrical, mechanical, sanitary and plumbing works, fire protection and alarm system
Completion Date : February 1996
    back to top »
 
Project : Integrated Microelectronics Bldg. G
Owner : Integrated Microelectronics Inc.
Location : Laguna Technopark
Scope of Work : Construction of a two-storey building with a total floor area of 5,120m².  Scope includes site development, civil, structural, architectural, electrical, mechanical, sanitary and plumbing works, fire protection and alarm system
Completion Date : July 1996
    back to top »
 
Project : Honda Cars Alabang
Owner : Honda Cars Makati, Inc.
Location : Madrigal Business Park, Muntinlupa City
Scope of Work : Construction of a 3-storey workshop with a showroom with a total floor area of 12,542m²  Works include civil, structural, architectural, electrical, mechanical, sanitary and plumbing works.
Completion Date : October 1996
    back to top »
 
Project : Integrated Microelectronics Bldg. B
Owner : Integrated Microelectronics Inc.
Location : Laguna Technopark
Scope of Work : Construction of a two-storey building with a total floor area of 8,000m².  Scope includes site development, civil, structural, architectural, electrical, mechanical, sanitary and plumbing works, fire protection and alarm system
Completion Date : June 1995
    back to top »
 
Project : Honda Cars Alabang
Owner : Honda Cars Makati, Inc.
Location : Libis, Quezon City
Scope of Work : Construction of a 2-storey building with a mezzanine floor and a a showroom at the groundfloor.  Works include civil, structural, architectural, electrical, mechanical, sanitary and plumbing works.
Completion Date : March 1994
    back to top »
 
Project : Honda Cars Makati
Owner : Honda Cars Makati, Inc.
Location : Magallanes Village, Makati City
Scope of Work : Construction of a 2-storey building with a showroom at the ground floor and a mezzanine.  Works include civil, structural, electrical, mechanical, sanitary and plumbing works.
Completion Date : April 1992
    back to top »
 
Project : Alexandra Condominium
Owner : Philippine Realty Holdings, Inc.
Location : Ortigas Center, Pasig city
Scope of Work : Construction of a 14-storey twin tower residential condominium with a roofdeck and basement parking common to the two towers. Approximate floor area is 35,952m² and with 104 residential units.  Scope includes civil, structural, architectural, electromechanical works.
Completion Date : October 1992
    back to top »
 
Project : QUAD II
Owner : Ayala Land, Inc.
Location : Ayala Center, Makati
Scope of Work : Complete renovation and expansion of three- storey commercial building with a floor area of 13,255m²        
Completion Date : June 1992
    back to top »
 
Project : La Isla Condominium
Owner : Greenhills Properties, Inc.
Location : Ortigas Center, Pasig city
Scope of Work : Construction of a 18-storey residential condominium with an approximate floor area of 18,768m².  Scope includes civil, structural, architectural, electromechanical works.
Completion Date : October 1992
    back to top »
 
Project : QUAD I
Owner : Ayala Land, Inc.
Location : Ayala Center, Makati
Scope of Work : Complete renovation and expansion of 36,000m² Quad theater arcade with ground floor as tenant area, two additional malls and bridgeways connected to Park Square 1 & 2         
Completion Date : October 1991
    back to top »
 
Project : DLSU Medical Center
Owner : De La Salle University
Location : Dasmariñas, Cavite
Scope of Work : Construction of a 4-storey hospital building with a floor area of 3,000 m².  Works include civil, structural, electrical, mechanical, sanitary and plumbing works.
Completion Date : February 1990
    back to top »
 
Project : Crisanta Towers
Owner : Silverland Realty & Development Corporation
Location : Pasig City
Scope of Work : Construction of a 13-storey residential condominium with an approximate floor area of 30,245m².  Scope includes civil, structural, architectural, electromechanical works.
Completion Date : April 1990
    back to top »
 
Project : Philippine General Hospital
Owner : Department of Public Works & Highways
Location : Manila
Scope of Work : Construction of a 8-storey central block building and other structures.
Completion Date : December 1988
    back to top »
 
Project : Najaf Hospital
Owner : Iraq Government
Location : Iraq
Scope of Work : Construction of a 7-storey hospital building with a floor area of 10,800 m².  Works include civil, structural, electrical, mechanical, sanitary and plumbing works.
Completion Date : April 1982
    back to top »